Hope & Clay Construction Ltd.




S278.BIZ

www.hopeandclay.com


St Georges Road, Wallingford


We confirm that we have been appointed by Wallingford School to carry out the S278 Roadworks at the above. These works include the alterations to the new car park entrsance and new drainafe


It is envisaged that the works will be completed within three weeks but may be subject to change due to factors beyond our collective control.


Advanced signing will be in place prior to the start date to inform the passing public of the impending works.


Works will commence on 9th August 2021 when traffic management will be installed.


The Road will be closed for the duration of the these works.


Drawings of the works can be found by clicking here.


Our Traffic Management Plans can be found by clicking here.