Hope & Clay Construction Ltd.




S278.BIZ

www.hopeandclay.com


London Road Horndean


We have been instructed by Vistry Group to carry out the additional S278 works at the above. The works include new paving to the footpaths, small drainage works and resurfacing of the carriageway


The works are programmed to be re-commenced on 14th November 2022 and will take approximately 4 weeks.


Traffic Management will be undertaken using a temporary set of two and three way traffic lights though out London Road. These traffic lights will be in use 24 hours a day 7 days a week for a period .


The Road will be closed to resurface the roundabout overnight from 20:00-06:00 for up to 5 nights from 5th December 2022. This will close the road on the A3 including the junction of the B2149 to resurface the roundabout. diversion will be in place. Access to residents and businesses will be maintained from one end of the works or the other.




The works drawing can be found here


Traffic Management plans can be found here


A signed Diversion route can be found here.