A348 Ringwood Road, Ferndown.


New M&S Store


We confirm that we have been appointed by Simons Construction to carry out the S278 Roadworks at the above. These works include the widening of the existing carriageway and the installation of a new pedestrian crossing point.


Associated Street Lighting and Street Furniture will be installed.


It is envisaged that the works will be completed within ten weeks but may be subject to change due to factors beyond our collective control.


Advanced signing will be in place prior to the start date to inform the passing public of the impending works.


Due to the sensitivity of the road, some works are to be carried out at night. Simons will keep the local community fully informed of these event. However these are identified on our programme of works.


Drawings of the works can be found by clicking here.


Our Traffic Management Plans can be found by clicking here.


The Envisaged Programme can be found by clicking here