Hounsome Fields Basingstoke - A30, Kempshott


New Major Roundabout


We confirm that we have been appointed by Vistry to carry out the S278 Roadworks at the above. These works include the realignment of the carriageway and a new Major Roundabout on the A30. The press release is available here.


Associated Street Lighting and Street Furniture will be installed.


These works are part of the Hounsome Fields Development.


It is envisaged that the works will be completed within fifty one weeks but may be subject to change due to factors beyond our collective control.


Advanced signing will be in place prior to the start date to inform the passing public of the impending works.


Works will commence on 14th September 2020 when traffic management will be installed. This will include closing the slip on the A30 from Winchester and a small Diversion via the traffic lights on the A30 Dummer Junction. Tree clearance will be undertaken at first followed by excavation and construction of the roundabout.



Drawings of the works can be found by clicking here.


Our Traffic Management Plans can be found by clicking here.


The Envisaged Programme can be found by clicking here