Dunmore Road, Abingdon.


New Signalised Crossing


We confirm that we have been appointed by David Wilson Homes to carry out the S278 Roadworks at the above. These works include the installation of a new signalised crossing on Dunmore Road, between Parsons Mead and Farm Road.


These works are part of the North Abingdon Development.


It is envisaged that the works will be completed within eight weeks but may be subject to change due to factors beyond our collective control.


Advanced signing will be in place prior to the start date to inform the passing public of the impending works.


Works will commence on 12th October 2020 when traffic management will be installed.



Drawings of the works can be found by clicking here.


Our Traffic Management Plans can be found by clicking here.


The Envisaged Programme can be found by clicking here


Up Date:- The Road has been reopened on 19th February 2021 and we are awaiting electrical connection to be able to bring the erected signals into operation.